The 14 DCMA points, one by one

A grid published by the US Defense Contract Management Agency and adopted in many contracts. It measures the structure of a schedule, not whether its content is right.

The fourteen points

PointWhat it measuresUsual threshold
1. LogicTasks with no predecessor or no successor5%
2. LeadsLinks still left open5%
3. Relationship typesThe share of links other than finish to start10%
4. LagsLinks with a waiting time5%
5. Negative lagsLinks with an overlap0%
6. Finish to startThe share of finish-to-start links90% or more
7. Hard constraintsImposed dates that prevent the calculation5%
8. High floatTasks with more than 44 days of total float5%
9. Negative floatTasks with negative total float0%
10. High durationTasks longer than 44 working days5%
11. Invalid datesConsistency of the logic along the critical pathNo break
12. Critical path length testWhat happens if a critical task slips by 600 daysThe project finish must move by as much
13. Baseline execution indexWork done against work planned0.95 to 1.05
14. Late tasksTasks that should be finished and are not5%

The three further checks

  • Calendars. A schedule that declares no non-working day and no public holiday computes dates that will not hold.
  • Milestones. A schedule with no start milestone and no finish milestone is attached to nothing.
  • Legibility. A 900-line Gantt chart on one page is not a schedule, it is a picture.

What the grid does not say

  • It does not say whether the durations are realistic. A perfectly structured schedule can be impossible to meet.
  • It does not say whether the content is complete. A forgotten task triggers no point.
  • It does not conclude. Klargantt gives the number, the threshold and the tasks concerned; it never writes "compliant".

Frequently asked questions

Are the thresholds mandatory?
No. They are the ones published in the assessment. A contract may impose others, stricter or looser.
Why 44 days?
That is the figure the grid uses: roughly two working months. Beyond it, a task is considered too large to be usefully tracked.