Total float and free float: read both

Two numbers, two different questions. Confusing them makes a blocking task look like a comfortable one.

What each one measures

Total floatFree float
The questionHow far can this task slip without moving the project finish?How far can it slip without moving its first successor?
What it looks atThe project finish, or the deadline that bounds itThe early start of its successors
When it is zeroThe task is on the critical pathAny delay gets in the way of what follows immediately
It can be negativeYes, when a constraint or a deadline cannot be metNo

An example

A task has 10 days of total float and 0 of free float. Moving it by a day does not push the project finish out, but it blocks its successor the next morning. On site, that is a task everyone believes is flexible and is not.

The reverse does not happen: free float never exceeds total float.

Why in working days

Float expressed in calendar days means nothing: five days across a four-day holiday weekend are not five days of work. Float is computed in working hours, then converted using the calendar of the task concerned.

What float does not say

  • 200 days of float does not mean the task is comfortable. It nearly always means a link is missing.
  • Negative float does not mean the project is late. It means an imposed date cannot be reached with the links as declared.
  • Float says nothing about resources: two tasks with comfortable float can need the same crew on the same day.